Environmental judgement means construction can start on SKB’s spent fuel repository

SKB has today received an environmental permit to build and operate the final repository for spent nuclear fuel in Forsmark and the encapsulation plant in Oskarshamn. The judgement was issued by the Land and Environmental Court, which is also granting SKB an enforcement order to enable initial work on the Forsmark area to begin at the turn of the year.

In January 2022, Svensk Kärnbränslehantering AB (SKB) was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Östhammar Municipality and an encapsulation plant in Oskarshamn Municipality. SKB has now reached another important milestone, with the Land and Environmental Court issuing its environmental judgement, which sets out the conditions under which the facilities are to be built and operated.

Stefan Engdahl, CEO Photo Mikael Wallerstedt

– This is a major milestone for SKB. We’ve now been given the means and the environmental conditions to build a safe and sustainable final repository for the spent nuclear fuel. This is important for Sweden and fossil-free electricity production, says Stefan Engdahl, CEO of SKB.

Enforcement order means that work can start

A key element of the court’s judgement is the granting of the enforcement order, which means that work can start at both sites, even if the judgement is appealed. The work that falls within the framework of the order, and which can start once the County Administrative Board in Uppsala County has approved the control programme, includes protective measures and preparatory work. In Forsmark, where the Spent Fuel Repository is to be built, this involves tree felling, excavation work for the operational area, the construction of space to store rock, the construction of a bridge over the cooling water channel, the backfilling of the operational area and nitrogen purification facilities.

– We need to establish the necessary infrastructure above ground and get started with earthworks and protective measures. SKB has proposed conditions that take into account nature and the surrounding area. We’re adapting to the nesting periods of birds, moving protected species so that they can continue to live at the site and building bioreactors that remove nitrogen from process water, says Stefan Engdahl, CEO of SKB.

Before SKB can start on the actual tunnelling process, an approved safety analysis report is required from the Swedish Radiation Safety Authority (SSM). Construction of the Spent Fuel Repository in Forsmark will begin two years before the encapsulation plant in Oskarshamn, as they have different construction times. Both facilities are expected to be ready for commissioning in the mid-2030s.

News

The conditions for SKB’s biggest construction project – the final repository for spent nuclear fuel – are now being established
In January 2022, SKB was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn. It is now time for the main hearing at the Land and Environment Court in Nacka on 17-20 S…

Published: 18 September 2024

International conference on repositories at Äspö
SKB is hosting a gathering of 50 nationalities to develop guidelines on how work can be undertaken at a global level on research and development of geological repositories for radioactive waste. The International Atomic Energy Agency (IAEA), which is part of the United Nations, is organising the con…

Published: 28 June 2024

High level of confidence and continued strong support for SKB’s facilities
Confidence in SKB is high and support for future final repositories remains strong. This is shown by Novus’ annual opinion survey in the municipalities of Oskarshamn and Östhammar. In spring 2024, SKB commissioned the research company Novus to conduct opinion surveys in the two municipalities where …

Published: 14 June 2024

Green light for SKB’s research programme
The Government has approved SKB’s latest programme for research, development and demonstration, RD&D 2022. Every three years, SKB presents a comprehensive research programme for the management and disposal of radioactive waste and spent nuclear fuel. The latest version was submitted to the Swedi…

Published: 10 January 2024

SKB signs collaboration agreement with Skanska for expansion of SFR
Illustration of the SFR showing the existing underground facility in white and the expansion in blue. SKB has signed a collaboration agreement with Skanska for expanding the existing final repository for short-lived radioactive waste (SFR) in Forsmark. The project involves the planning and construct…

Published: 21 August 2023

Published: 26 October 2024