This text is older than 7 years old and could contain inactive information.

The blue sections of this picture depict the new section of the Final Repository for Short-Lived Radioactive Waste, SFR, that SKB wants to extend into the bedrock under the sea.

One step closer to an extended SFR

The Land and Environment Court and the Swedish Radiation Safety Authority have announced SKB’s application for a licence to extend the Final Repository for Short-lived Radioactive Waste, SFR, in Forsmark.

– An extension of SFR creates capacity for final disposal of low- and intermediate-level waste from the decommissioning of the Swedish nuclear power plants. The announcement is another step on the way to fulfilling our important task, says SKB’s managing director Eva Halldén.

The application for permission to extend the existing SFR was submitted in 2014 and this week’s announcement means that the review continues and enters the next phase. The Land and Environment Court will now refer the application for comment to concerned regulatory authorities, organisations and other parties that will have an opportunity to offer comments on the matter. Thereafter, the case is tried under the Swedish Environmental Code in a main hearing, which is planned for the end of 2018.

– The material in our application shows that the facility as a whole will remain safe both during operation and in the long term. Now we look forward to the referral procedure in the spring and the planned main hearing later in the year, says Peter Larsson, project manager for the SFR Extension Project.

At the same time, the Swedish Radiation Safety Authority tries the application under the Nuclear Activities Act. The two licensing processes are pursued in parallel.

News

SKB to weld canisters for world’s first final repository
SKB is to weld canisters for the Finnish final repository for spent nuclear fuel. An agreement has been concluded between SKB and its Finnish counterpart, Posiva Oy, under which SKB will weld the bases of the Finnish canisters in SKB’s canister laboratory in Oskarshamn.

Published: 16 December 2024

Rock construction work can start on extension of SFR
On Friday the 29th of November SKB was granted a permit to commence rock construction work on the extension of the final repository for short-lived radioactive waste, SFR, in Forsmark. The permit was issued by the Swedish Radiation Safety Authority, SSM. In December 2022, Svensk Kärnbränslehantering…

Published: 5 December 2024

SKB International on state visit with the royal couple
SKB International is one of around 50 Swedish companies participating in the Swedish royal couple's state visit to Singapore. Magnus Holmqvist with Puah Kok Keong, Chief Executive, Energy Market Authority, EMA. Singapore is a country with ambitious goals to reduce its emissions and is working toward…

Published: 21 November 2024

Environmental judgement means construction can start on SKB’s spent fuel repository
SKB has today received an environmental permit to build and operate the final repository for spent nuclear fuel in Forsmark and the encapsulation plant in Oskarshamn. The judgement was issued by the Land and Environmental Court.

Published: 26 October 2024

The conditions for SKB’s biggest construction project – the final repository for spent nuclear fuel – are now being established
In January 2022, SKB was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn. It is now time for the main hearing at the Land and Environment Court in Nacka on 17-20 S…

Published: 18 September 2024

Published: 14 December 2017