This text is older than 2 years old and could contain inactive information.

Court grants licence for extended interim storage
in Clab

The Land and Environment Court has today granted SKB an environmental licence to increase the quantity of spent nuclear fuel in the Clab interim storage facility from 8,000 tonnes to 11,000 tonnes. Meanwhile, the licensing process under the Swedish Nuclear Activities Act continues.

Johan Dasht, SKB´s CEO. Photo: Mikael Wallerstedt.

— The environmental licence is a crucial step along the way for us to be able to receive more spent nuclear fuel in Clab. Now the parallel licensing process under the Nuclear Activities Act continues, for which the Swedish Radiation Safety Authority is responsible, says Johan Dasht, CEO of SKB.

The environmental licence may be utilised even if an appeal is lodged in higher courts. The limit under the current licence of 8,000 tonnes will be reached in December 2023. But to be able to go above this figure, SKB is required to submit updated safety analysis reports for approval by the Swedish Radiation Safety Authority. These must include reinforcements that further increase radiation safety at the plant.

— Both the Government and the court have now decided to grant SKB a licence for increased interim storage. These are important milestones, but considerable work remains to be done before we can guarantee continued interim storage, says Johan Dasht.

The fact that the licence for interim storage in Clab is being reviewed separately is a consequence of the Government´s decision to detach this issue from SKB’s overall final repository application last summer. Since then, SKB has undertaken extensive work to make the continued licensing process possible.

News

SKB to weld canisters for world’s first final repository
SKB is to weld canisters for the Finnish final repository for spent nuclear fuel. An agreement has been concluded between SKB and its Finnish counterpart, Posiva Oy, under which SKB will weld the bases of the Finnish canisters in SKB’s canister laboratory in Oskarshamn.

Published: 16 December 2024

Rock construction work can start on extension of SFR
On Friday the 29th of November SKB was granted a permit to commence rock construction work on the extension of the final repository for short-lived radioactive waste, SFR, in Forsmark. The permit was issued by the Swedish Radiation Safety Authority, SSM. In December 2022, Svensk Kärnbränslehantering…

Published: 5 December 2024

SKB International on state visit with the royal couple
SKB International is one of around 50 Swedish companies participating in the Swedish royal couple's state visit to Singapore. Magnus Holmqvist with Puah Kok Keong, Chief Executive, Energy Market Authority, EMA. Singapore is a country with ambitious goals to reduce its emissions and is working toward…

Published: 21 November 2024

Environmental judgement means construction can start on SKB’s spent fuel repository
SKB has today received an environmental permit to build and operate the final repository for spent nuclear fuel in Forsmark and the encapsulation plant in Oskarshamn. The judgement was issued by the Land and Environmental Court.

Published: 26 October 2024

The conditions for SKB’s biggest construction project – the final repository for spent nuclear fuel – are now being established
In January 2022, SKB was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn. It is now time for the main hearing at the Land and Environment Court in Nacka on 17-20 S…

Published: 18 September 2024

Published: 22 June 2022