This text is older than 3 years old and could contain inactive information.

Johan Dasht, CEO SKB.

Uncertainty concerning the continued interim storage facility and final repository process

The Government decided on 26 August to extract interim storage from SKB’s comprehensive final repository system application. The case is now with the Swedish Radiation Safety Authority and the Land and Environment Court for further investigation.

The situation surrounding the court process that awaits in the next step of the licensing process is still uncertain, but it is clear that SKB needs to collect extensive material to enable the interim storage section to be examined separately.

– We will naturally do our utmost to obtain an extended permit for the interim storage facility, thereby avoiding risks to electricity generation. We will simultaneously encourage the Government to come to a conclusion on the remaining areas of the final repository case, says SKB’s CEO Johan Dasht.

– We are particularly attentive to the fact that the Government has announced in the media that they may have a basis for making a decision on the final repository within a few months.

New safety analysis reports

The Swedish Radiation Safety Authority will also require new, comprehensive safety analysis reports that focus solely on the extension of the interim storage facility. The safety analysis reports previously submitted by SKB covered the final repository system in its entirety.

The safety analysis reports are put together in three stages. First, SKB will prepare a preliminary safety analysis report. Once this has been reviewed and approved, an updated safety analysis report will be drafted. This report must be approved before the facility may be put into trial operation. Following yet another safety analysis report, the facility may be put into regular operation. This comprehensive and advanced trial will now only be carried out on the interim storage facility.

In contravention to reviewing bodies

The Government had the opportunity to make a decision on SKB’s complete final repository system application but chose to extract and only deal with the section concerning licensing of increased storage capacity in the interim storage facility Clab in Oskarshamn. This was in contravention to what SKB, our owners and a large majority of the reviewing bodies deemed to be the best way forward. Among those who submitted comments were several regulatory authorities and the directly affected municipalities, Oskarshamn and Östhammar.

The decision to extract the section on interim storage rather than make a decision on the entire application entails risk, with unclear consequences. Therefore, on 31 August, Vattenfall renewed their warning to the electricity market that there may be cuts in generation starting in the spring of 2024. Time remains the critical factor as the interim storage facility under the current licence will be at maximum capacity as of December 2023. If no new permits are in place by then, the first reactor will need to be taken out of service soon thereafter.

A decision regarding the final repository is needed

SKB is commissioned with safely managing and disposing of spent nuclear fuel, both now and in the future. It is with great pride that we run one of Sweden’s most important environmental protection projects and we believe that we have a responsibility towards future generations to manage the waste generated by nuclear power.

News

SKB to weld canisters for world’s first final repository
SKB is to weld canisters for the Finnish final repository for spent nuclear fuel. An agreement has been concluded between SKB and its Finnish counterpart, Posiva Oy, under which SKB will weld the bases of the Finnish canisters in SKB’s canister laboratory in Oskarshamn.

Published: 16 December 2024

Rock construction work can start on extension of SFR
On Friday the 29th of November SKB was granted a permit to commence rock construction work on the extension of the final repository for short-lived radioactive waste, SFR, in Forsmark. The permit was issued by the Swedish Radiation Safety Authority, SSM. In December 2022, Svensk Kärnbränslehantering…

Published: 5 December 2024

SKB International on state visit with the royal couple
SKB International is one of around 50 Swedish companies participating in the Swedish royal couple's state visit to Singapore. Magnus Holmqvist with Puah Kok Keong, Chief Executive, Energy Market Authority, EMA. Singapore is a country with ambitious goals to reduce its emissions and is working toward…

Published: 21 November 2024

Environmental judgement means construction can start on SKB’s spent fuel repository
SKB has today received an environmental permit to build and operate the final repository for spent nuclear fuel in Forsmark and the encapsulation plant in Oskarshamn. The judgement was issued by the Land and Environmental Court.

Published: 26 October 2024

The conditions for SKB’s biggest construction project – the final repository for spent nuclear fuel – are now being established
In January 2022, SKB was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn. It is now time for the main hearing at the Land and Environment Court in Nacka on 17-20 S…

Published: 18 September 2024

Published: 22 September 2021