The Government approves SKB’s final repository system

Today, the 27th of January 2022, the Swedish Government decided to allow SKB to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn.

Johan Dasht, Managing Director of SKB. Photo: Mikael Wallerstedt.

– It is a historical decision that enables SKB to dispose of the nuclear waste that our generation has produced. This decision is met with open arms. We are now looking forward to implementing Sweden’s largest environmental protection project, says SKB’s CEO Johan Dasht.

The final repository project will bring investments of around SEK 19 billion and will create about 1,500 jobs. The projects will be financed by funds already funded from the Nuclear Waste Fund.

– For SKB, the decision further strengthens our position as a world leader in this area. The final repository also provides long-term solutions for electricity generation and is, thereby, our contribution to enabling fossil-free living within one generation, says Johan Dasht.

SKB has researched and developed technology for the final repository for more than 40 years in collaboration with experts from universities, research institutes and higher education institutions in Sweden and abroad. The final repository method was reviewed and assessed by the Swedish Radiation Safety Authority and the Land and Environment Court. The host municipalities, Östhammar and Oskarshamn, have also worked with these issues for a long time and have thereby taken considerable national responsibility for ensuring that Sweden has a functioning final repository system in place.

– Our application has undergone extensive review and it has clearly emerged that SKB’s final repository method satisfies the stringent safety requirements for man and the environment. We have a safe and secure final repository solution that we are very proud of, says Johan Dasht.

The next step in the licensing process is for the Land and Environment Court to establish conditions for the facilities. The Swedish Radiation Safety Authority will also decide on permit conditions under the Nuclear Activities Act. Only when all licences are in place can construction start, after which time, it will take about 10 years to build the spent fuel repository.

More information

Photo montage showing the final repository for spent nuclear fuel in Forsmark, above and below ground, seen from south east. The total length of the tunnel system is over 60 kilometers. Below ground the repository covers three to four square kilometers. It is placed at a depth of 500 metres.

News

SKB to weld canisters for world’s first final repository
SKB is to weld canisters for the Finnish final repository for spent nuclear fuel. An agreement has been concluded between SKB and its Finnish counterpart, Posiva Oy, under which SKB will weld the bases of the Finnish canisters in SKB’s canister laboratory in Oskarshamn.

Published: 16 December 2024

Rock construction work can start on extension of SFR
On Friday the 29th of November SKB was granted a permit to commence rock construction work on the extension of the final repository for short-lived radioactive waste, SFR, in Forsmark. The permit was issued by the Swedish Radiation Safety Authority, SSM. In December 2022, Svensk Kärnbränslehantering…

Published: 5 December 2024

SKB International on state visit with the royal couple
SKB International is one of around 50 Swedish companies participating in the Swedish royal couple's state visit to Singapore. Magnus Holmqvist with Puah Kok Keong, Chief Executive, Energy Market Authority, EMA. Singapore is a country with ambitious goals to reduce its emissions and is working toward…

Published: 21 November 2024

Environmental judgement means construction can start on SKB’s spent fuel repository
SKB has today received an environmental permit to build and operate the final repository for spent nuclear fuel in Forsmark and the encapsulation plant in Oskarshamn. The judgement was issued by the Land and Environmental Court.

Published: 26 October 2024

The conditions for SKB’s biggest construction project – the final repository for spent nuclear fuel – are now being established
In January 2022, SKB was granted permissibility and a licence by the Government to build a final repository for spent nuclear fuel in Forsmark in Östhammar Municipality and an encapsulation plant in Oskarshamn. It is now time for the main hearing at the Land and Environment Court in Nacka on 17-20 S…

Published: 18 September 2024

Published: 27 January 2022